Project
|
Location
|
Description
|
Estimate
|
Pre-Bid
|
Bid Opening
|
Project Manager
|
|
|
Central Macoupin County Rural
Water District
|
Macoupin
County
|
12 miles of
rural water main extension
|
$650,000
|
Spring 2008
|
Spring 2008
|
Bob
Manns
Jerseyville
|
|
Village
of Kane
|
Greene County
|
100,000 gallon elevated
water storage tank and wells
|
$900,000
|
Fall 2008
|
Fall 2008
|
Bob
Manns
Jerseyville
|
|
Greene
County Rural Water District IV
|
Greene
County
|
50
miles Rural Waterline Extension
|
$2,100,000
|
Winter
2008
|
Winter
2008
|
|
|
Staunton
Main Street Resurfacing
|
Staunton,
Illinois
|
Main
Street Resurfacing and Water Main Replacement
|
$730,000
|
Summer 2008
|
Summer 2008
|
|
|
CDB Centralia Correctional
Facility
|
Centralia,
Illinois
|
Wastewater Treatment Plant
Improvements
|
$340,000
|
Summer
2008
|
Summer
2008
|
|
|
Reconstruction
of
Independence Street
|
Cape
Girardeau,
Missouri
|
1.2
mile 44' PCC Roadway including storm sewer, water, sanitary
sewer, and sidewalk
|
$2,500,000
|
Summer
2008
|
Summer
2008
|
|
|
Fairgrounds
Avenue
Reconstruction
|
Jerseyville,
Illinois
|
0.9
mile 32' PCC Roadway including storm sewer, and sidewalk
|
$1,800,000
|
Summer/Fall
2008
|
Summer/Fall
2008
|
|
|
Snedeker
Road Reconstruction
|
Jerseyville,
Illinois
|
0.8
mile 32' PCC roadway including storm sewer and sidewalk
|
$1,600,000
|
2009+
|
2009+
|
|
|
Arenzville Rural Water
Coop
|
Arenzville, Illinois
Cass County
|
60 miles
|
$2,500,000
|
Summer
2008
|
Summer
2008
|
|
|
Shipman
Oil & Chip
|
Shipman
Macoupin Co.
|
Oil
& Chip
|
$15,000
|
Fall
2007
|
|
|
|
Medora
Oil & Chip
|
Medora
Macoupin Co.
|
Oil
& Chip
|
$9,000
|
Fall
2007
|
Fall
2007
|
|
|
Alma
Sanitary Sewer System
|
Village
of Alma - Marion County
|
Gravity
sewer system & wastewater treatment
|
$2,200,000
|
|
|
|
|
NE
Marion County Water Company - LaClede
|
Fayette
County
|
36
miles of rural water extensions
|
$1,100,000
|
August
2006
|
September
2006
|
|
|
NE
Marion County Water Company Phase II
|
Marion
& Clay Counties
|
92
miles of rural water extensions
|
$3,200,000
|
|
|
|
|
Fayette
Water Company Phase III
|
Fayette
County
|
110
miles of rural water extensions
|
$4,300,000
|
|
|
|
|
Village
of Mayestown
|
Monroe
County
|
Mayestown
new water well drilling
|
|
November
2005
|
December
2005
|
|
|
Village
of Iuka
|
Marion
County
|
Wastewater
Pump Stations - Rehabilitation
|
$400,000
|
July
2006
|
August
2006
|
|
|
Clay
County Water Company - Phase 2
|
Clay
County
|
100
miles of rural water extensions
|
$3,500,000
|
Fall
2006
|
|
|
|
Gateway
Regional Water Company
|
Clinton,
Marion, Wayne, & Clay Counties
|
Regional
3 MGD water treatment plant and transmission system
|
$16,450,000
|
|
|
|
|
Washington
County
Water Company
Phase VIII
|
Washington
County
|
70
miles of rural water
|
$2,000,000
|
|
|
|
|
Washington
County
Water Company
Bradley Township
|
Jackson
County
|
20
miles of rural water
|
$735,000
|
|
Spring
2006
|
|
|
Heritage
Woods Water Main Extension
|
City
of Centralia
|
10,500 LF of 6",
8", and 10" water main
|
$300,000
|
Summer
2007
|
Summer
2007
|
|
|
College
Ave. Sewer Improvements
|
City
of Centralia
|
2,200 LF of gravity sewer
replacement, lift station & force main
|
$425,000
|
Fall
2007
|
|
|
|